Monday, October 18, 2010

Water and Sewer Projects Overcome Challenges

Due to nice weather, the water and sewer projects are going forward at a fair pace.  However, two of the contractors have experienced some challenges.  On Cedar Street, MacArthur Construction discovered underground conditions to be very difficult with a layer of hard pan and flowing springs in the excavation area.  At the WWTF, the main building was more deteriorated than originally noted, and Merridian has had to accomplish additional repairs on the foundation, walls and windows.  The water tower project is on schedule.  Overall, MacArthur, Merridian, and CBI are doing a very credible job on these projects so far.  Thanks!

With any major project, unexpected items do arise.  City staff has regular progress meeting with the contractors.  The next meeting is on October 20, 2010.   If you have any questions or comments on these projects, please contact me.