Biosolids Tank Going Up

Meridian Construction is moving ahead tomorrow with the concrete pour for the bio-solids tank at the City's Wastewater Treatment Plant.  This is a very difficult task due to the weather and the work to be done.  The concrete forms have been enclosed in a temporary structure and are being heated to keep the area about 50 degrees.  This is necessary since the concrete will not reach the required strength, unless the temperature is warm enough.  Lee's Ready Mix is providing the concrete.

The concrete was not poured previously because the contractor did not have all the needed items due to shipping and supply problems.  The City is not paying additional costs for these problems.